Here is a general time line for constructing a timber frame home:
The following is a rough guideline for the construction of a new residence.
The order and time frame may vary from house to house depending on the size, location, time of year, design, and materials selected for the residence.
Some items will over-lap each other. This is to be used as a rough schedule.

Time Frame Phase
3-6 Months Design and engineering
OWNER to obtain all variances, surveys, perk tests, septic,
design and engineer, bank approvals, and all other details relating to the land and financinging
Clearing the site and stumping
  CONTRACT
Willy Vary Approx. 4-6 weeks Obtaining building, water, and sewer permits ** Order exterior windows and doors
Drilling well ( may be done prior to this or after this)
3-4 Weeks Excavation
Foundation, basement slab either now or after roofing
Backfill
4 Weeks First floor framing
Power to site
Timber frame raising
** Owner walk through for electrical locations
** Order tubs and showers
** Select other plumbing fixtures
1x8 roof decking installed
Panel application , rough wiring of exterior walls and ceilings
1 Week Roofing, fascias and eaves
Any masonry chimneys or facings to begin now
** Select final kitchen style and lay-out
1 Week Exterior windows and doors installed
2x6 T&G second floor installed
3 Weeks Temporary second floor stairs installed
Interior partitions
Install tub and showers
Basement stairs installed
** Final selection of plumbing and electrical fixtures
Rough plumbing and electrical
** Order kitchen cabinets and bathroom vanities
** Order unfinished wood floors
2 Weeks Heating, hot water
Siding
Installing any "0" clearance chimneys for fireplace inserts or
wood stoves
** Order stairs
2 Weeks Sheetrock
Septic ( or earlier)
** Order lights
** Order rest of plumbing fixtures
** Order other finished flooring
Depends on quantity Install unfinished wood floors
Sand and poly wood floors and 2x6 T&G second floor
2 Weeks Taping sheetrock
Install final second floor stairs
3 Weeks Paint
3 Weeks Install ceramic tile and pre-finished wood floors
Install cabinets and vanities
Trim
Hang interior doors
4 Weeks Final electric
Install any vinyl and carpet
Finish plumbing
Water test if well
Finish accessories
Final clean